  "docket": [
    {
      "decision": "IHMC Healthspan Center",
      "slug": "ihmc-233",
      "ref": "Triumph #233",
      "status": "Executed · mid-performance",
      "kind": "fact",
      "next": "PM#1 (expend ≥$58.5M research) due 2036-12-31; annual Oct-31 reports",
      "sids": [
        "S-23"
      ]
    },
    {
      "decision": "American Magic",
      "slug": "american-magic-315",
      "ref": "Triumph #315",
      "status": "Built · retained to build drone wings",
      "kind": "fact",
      "next": "Lease jobs deadline ≈ Jan 2029 if the DBO tracks the 2026-01-07 opening (inferred; DBO certificate wanted), else 2029-12-31. Triumph 170-job metrics due 2029. SailGP base opens Sept 2026 (trigger T3d). Saildrone's MUSV suit is pending in the Court of Federal Claims (filed late June 2026); the Navy's selected prototypes test through end-2026 — reported.",
      "sids": [
        "S-29",
        "S-07",
        "S-91"
      ]
    },
    {
      "decision": "UWF WAVE",
      "slug": "uwf-wave-330",
      "ref": "Triumph #330",
      "status": "GAA executed 2025-03-13",
      "kind": "fact",
      "next": "175 certificates + ≥$9.95M extramural due 2034-12-31",
      "sids": [
        "S-18",
        "S-90"
      ]
    },
    {
      "decision": "Birdon / Project Maeve",
      "slug": "birdon-367",
      "ref": "Triumph #367",
      "status": "PRE-EXECUTION — nothing binding yet",
      "kind": "open",
      "next": "GAA earliest Sept 2026 (not on Triumph's 2026-08-19 agenda — addendum 03 status check, 2026-08-13), then a 25-yr lease — both need City Council approval. Jobs ramp-up deadline 2035-12-31 if executed as drafted.",
      "sids": [
        "S-14",
        "S-07",
        "S-11",
        "S-45",
        "S-47"
      ]
    },
    {
      "decision": "HPMCE Dock Complex",
      "slug": "hpmce-dock-26-029",
      "ref": "Bid 26-029 · FSTED",
      "status": "Awarded · construction reported",
      "kind": "fact",
      "next": "180-day landside completion clock from notice to proceed ($500/day penalty)",
      "sids": [
        "S-16",
        "S-17",
        "S-15"
      ]
    },
    {
      "decision": "ST Titan / Project Titan",
      "slug": "st-titan-120",
      "ref": "Triumph #120",
      "status": "OPERATING · jobs clock not started",
      "kind": "fact",
      "next": "Hangar 3 due 2H2026; Hangar 4 under contract. Jobs clock = Hangar 4 occupancy + 5 yrs (Tier 1 may resolve ~2042, Tier 2 ~2052). §5.1 completion deadline passed 2025-04-29 — extension paper wanted (W-15). [Corrected 2026-08-13 (Run 03, R3-1): completion deadline is 2028-12-31 (Fifth Am.); it never lapsed — W-15 obtained. H4 construction start 2H2026 reported; DBO projected ~2027–28.]",
      "sids": [
        "S-41",
        "S-40",
        "S-55",
        "S-57",
        "S-52"
      ]
    },
    {
      "decision": "Port Road & Rail",
      "slug": "port-road-rail",
      "ref": "CDBG-DR HS002 + FSTED",
      "status": "UNDER CONSTRUCTION · deadline-tight",
      "kind": "fact",
      "next": "CDBG-DR funds must be expended by 2027-03-31; construction commenced 2026-03-01, ~12 months (little margin — recorded, no prediction). Standing council-agenda watch: any further HS002 amendment (the $1,950,000 road-paving line is marked \"PENDING AMENDMENT\").",
      "sids": [
        "S-60",
        "S-61"
      ]
    }
  ]
}